Organization – Heavy Water Board (HWB), Department of Atomic Energy (DAE), Tuticorin
Project – Integrated Solvent Plant (IS) Project
Scope of TEL – Design Basis Report, HAZOP, Design Calculation, Analysis, Detailed Engineering, Bill of Material, Technical Specifications, Procurement, Fabrication, Manufacturing, Testing, Inspection & Expediting at Supplier’s Works, Spares, Site Fabrication, Safe delivery at Site, Security of Supply items at Site, Erection, Installation, NDTs, Hydrotesting, Functional Testing, Pre-Commissioning, Performance Test Run, Operation and Maintenance Manual of Supplied Items, As Built Drawings, Project Management including Fiscal and Physical Progress Schedule.